What documents are needed when applying for an ECC? PDF Print E-mail

  • Specific document requirements can be found in Annex 2-1a Table 3 pages 56-57 of the Revised Procedural Manual for DENR Administrative Order No.30 Series of 2003 (DAO 03-30)

  • However , if you are located within the Laguna de Bay area, document requirements were the same as above , except for some additional attachments ( since the application will be for both ECC and LLDA Clearance)

    • Under DENR MC 2007-08, no permits and/or clearances issued by the National Government Agencies and LGUs shall be required in the processing of ECC or CNC applications.

    • Likewise, findings and recommendations of the EIA shall be transmitted to relevant government agencies for them to integrate in their decision-making prior to the issuance of clearances, permits and licenses under their mandates.

    • Thus, with or without the following requirements, the ECC/CNC applications shall be processed/issued: Water Permit from NWRB, Locational Clearance from LGU/HLURB, EGGAR/GAR approved by MGB.

    • Submission thereof 45 days from receipt of approved clearance, will form part of the ECC/CNC conditionalities.

  • LLDA Clearance may be secured/issued after the ECC issuance, i.e. it is not a pre-requisite to an ECC (DENR Memo-Clarification dated January 29, 2008).